Container street permit in Rosemont–La Petite-Patrie
To place a container on the street, sidewalk or alley in Rosemont–La Petite-Patrie, a temporary occupancy permit is required. Expect about $905 tax included for 10 days (residential container, up to 49 m²). In a private driveway, no permit is required.
How much does a container permit cost in Rosemont–La Petite-Patrie?
A 20-yard container takes up about 16 m²: the “up to 49 m²” rate applies to nearly every residential rental.
- Minimum lead time
- 10 business days
- Maximum validity
- 1 an
- Daily rate (up to 49 m²)
- $73.00 · tax incl.
- $73.00 × 10 days
- $730.00
- Issuance fee
- $59.00
- Analysis fee
- $116.00
- Subtotal · tax incl.
- $905.00
Note: Frais d'analyse de 116 $, les plus élevés de l'île. Demande à recevoir 10 jours ouvrables à l'avance. Corridor piéton ou cycliste balisé d'au moins 1,5 m obligatoire si obstrué.
https://montreal.ca/demande-permis/occupation-temporaire-domaine-public/demande
The amounts published by this borough already include tax.
What does the permit cost in comparable boroughs?
Boroughs with the same lead time, ranked by closest cost.
- Container permit in Le Plateau-Mont-Royal$885 for 10 days
- Container permit in Le Sud-Ouest$794 for 10 days
- Container permit in Saint-Léonard$750 for 10 days
Which size for your project?
Data source: montreal.ca